Barrick Produced 1.90 Million Ounces Of Gold In Q3, 2009
TORONTO, ON - Barrick Gold reported Q3 2009 production of 1.90 million ounces at total cash costs of $456 per ounce was on plan, primarily as a result of strong operating performance from North America and South America. The Company is on track with its full year production guidance of 7.2-7.6 million ounces of gold at total cash costs of $450-$475 per ounce or net cash costs of $360-$385 per ounce.
The
Barrick's three world-class projects in construction remain on schedule and in line with their respective pre-production capital budgets. Together with Buzwagi, they are expected to collectively contribute about 2.6 million ounces(3) of lower cost average annual production once at full capacity. Production is expected to increase to 7.7-8.1 million ounces in 2010 with new production from Cortez Hills(4).
Overall construction of the Cortez Hills project in
The Pueblo Viejo project in the Dominican Republic is progressing well and is in line with its pre-production capital budget of approximately $2.7 billion (100% basis)(5), with approximately 60% of the capital committed. First gold continues to be expected in Q4 2011. Site demolition is now complete and earthworks are about 80% complete. Autoclave construction and steel erection on the autoclave building is well advanced and the first of the mills have arrived in the
Pascua-Lama has recently entered construction, with the project team mobilizing to site and beginning work on installation of construction infrastructure. Orders have been placed for long lead time items including mills, the Chilean camp, and mining and earthworks equipment. Pascua-Lama is expected to produce about 750,000-800,000 ounces of gold and 35 million ounces of silver annually in its first full five years at anticipated total cash costs of $20-$50 per ounce(6), making it one of the lowest cost gold mines in the world. Commissioning is expected in late 2012 and initial production in the first quarter of 2013.
A draft feasibility study on the Cerro Casale project in
Barrick recently entered into an agreement to acquire Xstrata Plc's 70% interest in the El Morro project for $465 million in cash. El Morro is expected to add another large, high quality gold-copper resource to Barrick's portfolio in
The
The Australia Pacific region produced 0.46 million ounces at total cash costs of $585 per ounce. Porgera, the region's largest operation, produced 0.12 million ounces at total cash costs of $583 per ounce. Higher production and lower total cash costs are expected at Porgera in Q4.
Production from the African business unit was 0.21 million ounces at total cash costs of $477 per ounce with a strong contribution from the new Buzwagi mine, which produced 87,000 ounces at total cash costs of $315 per ounce. The flotation plant was commissioned during Q3 and processing is expected to transition from oxide to sulfide ore in Q4. Buzwagi is anticipated to produce about 200,000 ounces of gold at total cash costs of about $335 per ounce in 2009.
The Company is on track with its full year copper production guidance of 375-400 million pounds and is expecting to come in at the low end of its total cash costs guidance of $1.25-$1.35 per pound. Q3 copper production of 104 million pounds was on plan and total cash costs of $1.05 per pound were better than plan. The Company again benefited from its copper hedge position, realizing $2.90 per pound, 9% higher than the average spot price.
The company’s address is