Blackwater Project Construction Fleet Scheduled For Delivery


VANCOUVER - Artemis Gold Inc. reported that the Blackwater construction fleet has been ordered and expected to be delivered in early Q2 2023 and will be composed of a variety of mining support equipment, including excavators, backhoe loaders, compactors, graders, telehandlers, as well as fuel and water trucks, and will be further expanded throughout the construction period.

Supplementary rental equipment will be used in the interim to support the initial construction fleet until the primary mining fleet is delivered to site in preparation for the commencement of mine pre-stripping activities. Preliminary work activities will focus on development of site infrastructure including access roads, water management structures, mine haul roads, and commencement of tailings dam construction.

The plant site preparation is well advanced with the majority of the bulk earth works completed, including contractor laydown and batch plant areas. Both areas are ready for handover to the Engineering, Procurement and Construction contractor. Meanwhile, construction activities have expanded to focus on water management in readiness for spring breakup, including completion of the sediment and erosion control pond.

The process plant site  area remains on track to be completed before the start of major works construction, which is expected to commence shortly following the receipt of the BC Mines Act Permits.

Work on the construction camp is proceeding on schedule with 150 rooms and kitchen facilities on track to be ready for occupation by the end of February, with the remaining rooms to be furnished and ready for occupation in March 2023, bringing the total camp capacity to 477 beds to meet the full complement needed for the duration of the construction period.