Demonstration Plant Begins Testing Process Improvements And Rare Earth Recovery Operations
CENTENNIAL, CO - NioCorp Developments Ltd. reported that its demonstration-scale processing plant in Quebec, Canada is now processing ore samples from the it’s Elk Creek Critical Minerals Project. The demonstration plant project is intended to demonstrate that the Company can extract and separate rare earth elements from ore that NioCorp expects to mine from the Project site, subject to receipt of necessary project financing, and that its simplified process for potentially producing niobium, scandium, and titanium is technically and economically feasible.
The demonstration plant will process Elk Creek ore samples in three phases. Testing is expected to be completed over the next several weeks. NioCorp expects to publicly disclose testing results after each operational phase concludes.
Phase 1 is designed to demonstrate a new approach to the initial processing of the ore that NioCorp expects to mine from the Project site, subject to receipt of necessary project funding, including calcination, initial leaching, and rare earth extraction. Phase 2 is designed to demonstrate an improved process for the second stage of leaching along with Niobium and Titanium separation. Phase 3 is designed to demonstrate the technical viability of separating high-purity versions of several target magnetic rare earth products from Elk Creek ore samples, as well as confirming previously achieved high recovery rates for high-purity Scandium trioxide. The potential magnetic rare earth products include Neodymium-Praseodymium (“NdPr”) oxide, Dysprosium oxide, and Terbium oxide. NioCorp will utilize conventional solvent extraction (“SX”) technology to test a rare earth separation approach developed by NioCorp and L3. NioCorp and L3 have years of collective experience in SX technology.
“Our team is very pleased to see the demonstration plant begin operations, and we intend to closely monitor every step of this process,” said, Scott Honan, COO. “Many of these processes have already been successfully tested at the bench scale. Given our team’s years of experience in hydrometallurgy, including rare earth separations, I expect that we will demonstrate positive results. I also look forward to potentially demonstrating how our simplified process flow sheet can more efficiently and cost-effectively produce Niobium, Scandium, and Titanium. Once operations have concluded and data analyzed, work can then turn to the design and engineering of the new process flow sheet, which in turn is expected to be incorporated into an updated Elk Creek Project Feasibility Study that incorporates an economic analysis of separated rare earth oxide products and the simplified process flow sheet.”
As no economic analysis has been completed on the rare earth mineral resource comprising the Project, further studies are required before determining whether extraction of rare earth elements can be reasonably justified and economically viable after taking account all relevant factors.