Johnson Camp SX Plant Start-Up With First Copper Sales

PHOENIX, AZ – Gunnison Copper Corp. reported that the solvent extraction (SX) plant and electrowinning (EW) circuit has started with first copper sales expected in September at theJohnson Camp Mine (JCM), in southeast Arizona.
“With the start-up of the SX-EW plant ahead of schedule we have achieved another major step towards our targeted copper cathode sales in September this year,” states Robert Winton, SVP Operations.”The dedicated team at Johnson Camp has executed this startup without incident and in record time, preparing for our first harvest of Made-in-America copper to be sold in Q3 this year.”
Progress as of the Company’s last update includes: Leaching of mineralized run-of-mine material started with copper rich solution being pumped to the SX-EW plant; SX Plant started; and EW Circuit started and being readied for Copper Plating.
Since the last update, the JCM construction activities continue to progress as planned. The final phase of the leach pad construction is on schedule. The on-pad crushing circuit, which will be used with the Nuton Technologies, has been installed and started commissioning activities. The agglomerator and processing equipment, which will also be used on the Nuton pad, has been placed and the Company is completing final mechanical and electrical construction of these components. The new LNG (liquid natural gas) system at the EW plant was fully commissioned and operating in line with electrowinning start-up.

Add Your Heading Text Here

Add Your Heading Text Here

Back To Top