New Growth Stage With The Rochester Expansion Project
CHICAGO, IL - Coeur Mining, Inc. reported on the current operations at the Rochester mine. The Coeur Rochester mine is an open pit, heap leach silver-gold operation, located in Pershing County, Nevada. The mine consists of the main Rochester deposit and the adjacent Nevada Packard deposit southwest of the Rochester mine and the Lincoln Hill, Gold Ridge, and Wilco projects. Operations at the Rochester mine initially began in 1986 and were briefly suspended from 2007 through 2010. In 2011, the entire mining operations and production resumed and have continued to grow ever since. Coeur Rochester employs more than 370 mining professionals and is the largest employer in Pershing County.
The Company announced the achievement of several critical milestones at its major Rochester expansion project in Nevada, including the production of the first silver and gold ounces. Following a ramp-up period expected to last into early 2024, Rochester is expected to drive a step-change in the Company’s overall production levels, cost profile, and cash flow.
Metal production from the new Stage VI leach pad and Merill-Crowe process plant leach began mid-month with initial doré expected to be poured today. Approximately one-third of the eight million tons of ore on the new pad are currently under leach. The Merrill-Crowe plant is achieving a flow rate of roughly 3,500 gallons per minute (gpm) of solution. Full ramp-up to commercial production of around 13,000 gpm is expected to be achieved in early 2024. With the primary gyratory crusher now installed, construction of the new three-stage crushing circuit is now substantially complete. Once fully ramped-up, throughput is expected to average 32 million tons per year, which is approximately 2.5x higher than historical levels, making Rochester one of the world’s largest open pit heap leach operations A multi-day test of truck and loading capacity was completed to ensure that the mine can support the higher throughput rates associated with the newly-configured Rochester circuit. This test confirmed the mine’s ability to safely support the designed capacity of up to 100,000 tons per day in 2023 and up to 132,000 tons per day in 2024. Data gathered during the test will be used to refine processes and identify opportunities for additional efficiencies in cycle and load counts.
“The achievement of these three critical milestones marks the beginning of a new growth phase for Coeur,” said Mitchell J. Krebs, President and Chief Executive Officer. “The focus is now shifting to commissioning, ramp-up, and mine optimization initiatives as well as prioritizing several adjacent exploration targets located on Rochester’s prospective 69-square mile land package. Coeur’s project team has overcome numerous challenges over the last three years to arrive at this key inflection point and deserves thanks for their resilience and commitment.”